CHC CLONGRENNANE
Project Overview
- Supply of a new 150mm Natural Gas Pipeline
- The Mechanical works involved the supply of a 100mm carbon steel pipeline from AGI station to Kiln’s at factory production area.
- A valve insolation station was installed in a “Cubis” manhole chamber with a 100mm underground pipeline for
- Pipeline was servisleeve wrapped and holiday detected on site.
- The above ground 350m pipework sections were fitted to steel supports with their final connections at kiln’s.
- A sacrificial anode system was installed with underground pipework to IS. EN12954 with IK gaskets at flanges and IP65 junction
Project Standards
- All pipeline works x rayed to ASME 9 standard.
- This project was tested and commissioned and signed off to gas networks Ireland requirements.
- All work carried out at a live plant with no disruption to plant activities.

