CHC CLONGRENNANE

Project Overview​

​

  • Supply of a new 150mm Natural Gas Pipeline​
  • The Mechanical works involved the supply of a 100mm carbon steel pipeline from AGI station to Kiln’s at factory production area.
  • A valve insolation station was installed in a “Cubis” manhole chamber with a 100mm underground pipeline for ​
  • ​Pipeline was servisleeve wrapped and holiday detected on site.​
  • The above ground 350m pipework sections were fitted to steel supports​ with their final connections at kiln’s.​
  • ​A sacrificial anode system was installed with underground pipework to IS. EN12954 with IK gaskets at flanges and IP65 junction 

Project Standards​

  • All pipeline works x rayed to ASME 9 standard.​
  • This project was tested and commissioned and signed off to gas​ networks Ireland requirements.
  • All work carried out at a live plant with no disruption to plant​ activities.