BELFIELD MEETING PODS

Meeting high expectations

When Structuretone appointed us for the Cat-B mechanical fit-out of two high-spec meeting pods to NZEB standards, to include stand-alone heat pump systems supplying wall-mounted heating/cooling units, we knew we faced challenges – not least Covid-19 restrictions.

However, moments like these prove the value of 60 years of experience. Having a local network of resources allowed us to get the maximise work done while the sites were open.

Year
2021

Size
  45 m2

SCOPE OF INSTALLATION WORKS

Heat pump system with convector
Car park extract ventilation system
Water services to irrigation systems
Storm water piping network
Fire extinguisher installation