The recent appointment of McKeon Bros to take charge of the large scale, mechanical services retrofit project at Belfield Blocks 7 & 8 reflects the confidence that main contractors and design teams have in our ability to deliver work of the highest standard; work that delivers their promises.

However, we believe our experience at two similar office blocks at the Belfield campus was another significant factor in McKeon Bros being selected for this high-profile project.

Challenging on so many levels

McKeon’s were awarded the contract for the fast-track retrofit of Belfield Blocks 7 & 8, to make them suitable as a corporate HQ for a prestigious client. This work involved decommissioning and stripping out the existing services across 6,000 square metres of office space on eight floors and upgrading them to a high spec CAT B standard… and all within 16 weeks.

Planned to succeed

Success in any project requires meticulous planning, experienced and focused management, high levels of teamwork and full co-operation between all parties. Put a very tight deadline into the mix, and lines of communication become vital. With a multidisciplinary workforce onsite, everyone needed to know exactly what was required of them – and when.

The seemingly impossible, made possible

What our client needs, our client always gets. Over the decades, we’ve earned a reputation for our ‘can-do’ approach; meeting critical deadlines, delivering as required by clients, and as promised by McKeon Bros.  We’re pleased to report, that in true McKeon Bros tradition, the project was completed within the timeframe and handed over to our client.

 

Read: Hybrid AHU in Belfield – A first in Ireland 

In partnership with Flynn Management Contractors Ltd., Axis Engineering, Henry J. Lyons Architects and Linesight QS, McKeon Brothers Ltd. recently completed the refurbishment and fit out of the basement of 123 St. Stephen’s Green, which forms part of the Royal College of Surgeons in Ireland’s (RCSI) campus.

The scope of the project was to supply, install, set to work, test and commission all mechanical systems throughout all areas.

The works comprised of:

  • Strip out of the basement area of 123 St. Stephens Green back to ‘grey box’ condition
  • Fit out of the basement area to accommodate a new commercial kitchen and server, canteen and associated break-out areas
  • Ancillary works and associated mechanical and electrical and building fabric upgrades

Conducted over the course of five months, the mechanical services included in the works were:

  • VRF System
  • Ventilation supply and extract systems
  • Air handling units
  • Toilet extract ventilation systems
  • Café extract ventilation systems
  • Kitchen ventilation
  • Compensated radiant heating in the WC
  • Low temperature hot water pipework distribution
  • Acoustic and vibration control
  • Mechanical Control Centres, Controls, BMS outstations field devices and interface with packaged plant
  • General Metalwork
  • Internal gas distribution from the Boiler Room to the kitchen
  • Gas detection in Kitchen
  • Water services
  • Drainage
  • Hand-held firefighting installation
  • Commissioning, balancing, treatment and sterilisation of the mechanical services systems

The project was successfully completed in January 2018.